Monday 30th July 2018

Update: Loss of utility power at FRA1 / FRA1.1 is still running on generators

The power for our FRA1.1 Data Centre continues to be provided by generators in an N+1 redundant configuration. Stability has been maintained throughout with no interruptions.

During the course of the implementation our provider have experienced unexpected technicalities which have introduced some delay. Consequently a decision has been made to extend the timeframe to complete the installation and commissioning of the temporary generator to tomorrow morning. Our data center provider estimates that works will be completed by mid-morning, including the transfer of the work load back to utility power as per previous communications.

Root cause analysis of the transformer failure continues. More updates will follow pending the availability of information.