Tuesday 31st July 2018

Update: Loss of utility power at FRA1 / FRA1.1 is still running on generators

We would like to inform you that the power for our FRA1.1 Data Centre continues to be provided by generators in an N+1 redundant configuration. Stability has been maintained throughout with no interruptions.

Our data center provider has successfully completed the installation of the temporary generator. The technicians are performing several tests before they start the transfer of the work load back to utility power this afternoon, pending successful completion of these tests.

Root cause analysis of the transformer failure continues. More updates will follow pending the availability of information.

The next update will be later this afternoon after completion of load transfer to utility power.